Timeline

Project Programme

An outline project programme identified the following timescales and key dates for the delivery of the new Community Hub project.

Q2 2021

Initial Engagement

Pupils / Parents / Staff / Police Scotland

Q2 2021

NLC Stakeholder Consultation

Q2 2021

School Engagement Events

Q2 2021

Wider Community Consultation

Q2 2021

Community Groups Consultation

Q3 2021

Final Intelligent Brief Consultations

Pupil / Parents / Staff. “You said / We Did”

Q4 2021

Intelligent Brief Submitted

Q4 2021

Tier 1 Contractor Appointed

Q1 2022

PAN Submitted

Q2 2022

Community Consultations

Pupils, Parents, Staff and Community

Q3 2022

Planning submission

Q3/Q4 2022

Detail Design Stage

Q2 2023

Site Start

Q3 2024

New Build Complete

Q1 2025

Existing Schools Demolished

Q3 2025

Landscaping Complete

“Every session planned for consultation; the Keppie team came armed with inspiring digital presentations, colourful feedback sheets and outdoor activities. All were exciting and captured the imagination of learners. The cross section of pupils allowed the good majority of pupils and staff ‘a voice’ to share their hopes and dreams for the future learner and worker in Bellshill. We were all delighted by the professionality of the team but also the respect and interest in our feedback.”

K Somerville, Head teacher
Sacred Heart Primary, Sacred Heart and Orbiston Nurseries

Proposed Site Phasing